LATEST PROGRESS UPDATES ON PIXEL
- Internal and external finishes have been completed
- Hard & soft landscape has been completed
- MEP systems have been tested and in the final stage of handover to relevant authorities
- BCC is in its final stage of being obtained
- Facility management of all buildings has been mobilized