ALJURF GARDENS
CONSTRUCTION UPDATES Q1 2023
Phase 1
- Roads and infrastructure work completed, with ongoing handover to the concerned authorities
- All villa foundations completed
- All villa concrete structures completed
- 50% of the villas' external stone cladding work completed and an invoice will be issued accordingly
- Internal finishes work ongoing in villas
- External façade finishes work ongoing in villas
- Anticipated handover date is Q2 2023
- To ensure the project keeps progressing well according to the time plan and to the highest international standards, a bank facility is signed with First Abu Dhabi Bank, also mortgage agreement for the units against the bank facility to fund and complete Al Jurf Phase (1.2) project. As a result of this a minor change need to be made to the existing Sale and Purchase Agreement. The change should not affect the Purchaser in any way. One of our team will be in contact soon to assist you in signing an amendment giving effect to these changes.
Phase 2
- Enabling works completed
- Site grading and leveling completed
- Foundation work expected to be completed in May 2023 with invoices to be issued accordingly
- Anticipated handover date is Q3 2024